Hugo Boss

  • IMG
  • IMG
  • IMG
  • IMG
  • IMG
  • IMG

hugo boss logo - Hugo Boss

Project Details

  • Project Value – £ 16k
  • Duration of Works – 10 Days
  • High-end Reatil strip out back to build base core
  • Team – 5 Men
  • Total Waste Cleared – 38 Tonnes
  • Site Safety – 100%
This central London Hugo Boss store was completely stripped out, ready for a new tenant re-fit.
  • 3D were tasked to strip out and remove all shop fitting fixtures and fittings.
  • A complete strip out of the dry lined walls, MF ceiling and tiled flooring was carried out.
  • All power, alarms and data were removed.
  • A clean slab to slab was handed over.

3D Stripout are passionate about providing a professional stripout service of the highest standard. Due to our professional and personal approach, we are able to create long standing and successful relationships with our clients as well as main contractors. We highly consider safety, noise and full consideration to the client and public on every project. Our team are available 7 days a week, in or out of hours. Let us use our hands-on approach to ensure you receive the best possible service for your stripout project! When you choose 3D Stripout, you do not have to worry about a negative impact on the environment. We work hard to ensure that our services to do harm our precious Earth. Our team are able to do this by recycling as much waste as we can and by sorting it on site. This ensures that no waste is double handled by our waste partners. Call us today to find out more: 0345 122 1220.