IPS – North London

  • strip out of hall
  • IPS
  • IPS
  • IPS

Project Details

  • Project Value – £ 8k
  • Duration of Works – 3 Days
  • Partial soft strip out of tenat let offices
  • Team – 3 Men
  • Total Waste Cleared – 18.2 Tonnes
  • Site Safety – 100%
This commercial office was stripped out on behalf of IPS with 3D as nominated strip out sub-contractor.

  • 3D Strip Out were tasked to strip out and remove all fixtures, fittings, partitioning and floor covering.
  • A clean access floor was handed over.