L&C National Express

  • Nat Exp  Large

Project Details

    • Project Value – £ 28k
    • Duration of Works – 12 Days
    • Complete office floor strip out of all partitioning, small power and flooring
    • Team – 6 Men
    • Total Waste Cleared – 36 Tonnes
    • Site Safety 100%

A complete soft Strip Out of the pre-let Head Office for National Express was carried out by 3D. All desks and furniture were removed and fully recycled prior to the main partitioning demolition. It was decided by the client to retain the carpet tile floor covering. The floor was stripped out in 6 working days and all waste was removed via the service lift.The purpose of this part strip out was to show potential new clients the space available to let.

 

3D Stripout are passionate about providing a professional stripout service of the highest standard. Due to our professional and personal approach, we are able to create long standing and successful relationships with our clients as well as main contractors. We highly consider safety, noise and full consideration to the client and public on every project. Our team are available 7 days a week, in or out of hours. Let us use our hands-on approach to ensure you receive the best possible service for your stripout project! During our project we always keep the environment in mind. This means that we reduce and recycle as much waste as we can and we also ensure to sort any waste on site. This will ensure that it does not get double handled by our waste partners. To find out more, call our team today: 0345 122 1220!

Paste your AdWords Remarketing code here