Putney Station – Bar & Brassarie, Putney London

  • Putney Station
  • IMG  aebbdadeaef
  • Putney Station
  • Putney Station

Project Details

  • Project Value – £ 16k
  • Duration of Works – 14 Days
  • Complete Cat “A” bar / pub strip out
  • Team – 5 Men
  • Specialists – AC degas & F-Gas recovery
  • Total Waste Cleared – 31 Tonnes
  • Site Safety – 100%
This bar / restaurant premises was completely stripped out, ready for a planned refit by Urban Leasure group.

  • 3D were tasked to strip out and remove all shop fixtures, fittings,commercial kitchen with extraction system and all WC blocks.
  • A complete strip out of the dry lined walls, MF ceiling and wooden flooring was carried out.
  • The AC system were de-gassed and removed.
  • A clean site was handed over.

3D Stripout are passionate about providing a professional stripout service of the highest standard. Due to our professional and personal approach, we are able to create long standing and successful relationships with our clients as well as main contractors. We highly consider safety, noise and full consideration to the client and public on every project. Our team are available 7 days a week, in or out of hours. Let us use our hands-on approach to ensure you receive the best possible service for your stripout project!

Not only do we work hard to ensure that your project gets completed to the highest standard,  but we also take the environment into account. We work hard to make sure that our work does not have a negative impact on our wonderful Earth. Our team are able to achieve this by sorting our waste on site, so that it does not get double-handled by our waste partners.

 

Paste your AdWords Remarketing code here